The words change parts included need an inventory behind them. Loose tooling can be difficult to identify after a machine has been dismantled. Build a photographed register that ties each part to a bottle, closure and operating format before collecting the equipment.
Make one record for each production format
Give every intended bottle-and-closure combination its own row. Record bottle diameter and height from its drawing, finish reference, closure drawing and intended output. Keep a separate field for the format demonstrated on the offered machine. This prevents a previous owner's format list from becoming an untested promise for your own production.
Photograph the handling parts as sets
Ask which infeed screws, starwheels, guides, supports or other format components are fitted or supplied loose. Use the machine documentation to establish which are relevant. Photograph identification marks and package the parts as named sets rather than as an undifferentiated box of spares.
| Register field | Useful entry |
|---|---|
| Part identity | Photograph, marking and quantity |
| Format association | Bottle and closure drawing references |
| Evidence | Installed, demonstrated, loose or unconfirmed |
| Supply scope | Included, optional or excluded |
Keep head setup evidence with the tooling
Request identification of the installed heads and available setup records. AROL describes dedicated tools for head setup, monitoring and calibration; that supports asking how the offered machine was checked. It does not establish that a particular used machine includes those tools or has a current verification record.
Observe a changeover rather than timing an empty adjustment
Where an inspection allows it, follow a change from one agreed format to another. Record parts replaced, settings changed, sample checks and the point at which acceptable output resumes. Keep operator work and waiting time visible. A short adjustment demonstration is different from a complete production changeover.
Close the register before dispatch
Reconcile the photographed list with the quotation and packing list. Put missing, damaged or unidentified parts in a separate action list with an owner and estimated scope of work. Retain the register with the machine documents so the receiving team can check the delivery without reconstructing the sale from photographs.
Buying checklist
- One row for every proposed bottle-and-closure format
- Photographed and labelled handling sets
- Installed-head identification
- Available setup records and supplied tools
- Observed changeover tasks and production checks
- Packing list reconciled with the agreed tooling register